BC Hydro Calls for Power
1.5 TWh/yr more wind and solar in 2025, up 20% on 2024
Peace
South Interior
East and West
North Coast
Central Interior
Vancouver Island
2024 Call for Power
Awarded December 2024
Weighted average bid price of awarded contracts
$86/MWh
Evaluation price $83/MWh
CEAP interconnection cost
$60M
Average per winner
$6.40 per MWh
$68M
Average per bidder
$9.80 per MWh
2025 Call for Power
Awarded May 2026
Weighted average bid price of awarded contracts
$95/MWh
Evaluation price $94/MWh
CEAP interconnection cost
$40M
Average per winner
$2.70 per MWh
$113M
Average per bidder
$10.05 per MWh